Home

The Premier International Club in Asia

 

News

February

Following the end-of-year celebrations and a 10-day holiday break, work on the new Club building resumed with gusto on January 4. As the steel erection and concrete pouring continued on the aboveground floors, finishing work began on the basement levels.

Read More

December

The end of the year was commemorated on the construction site with a large-scale mochi tsuki ceremony on December 25. Hundreds of workers took part in the auspicious New Year custom, pounding steamed rice into a sticky paste with a heavy mallet.

Read More

October

After a little more than one year of construction and just over a year to go before the new Club is completed, progress of the facility is on schedule. While construction was delayed earlier in the year by the discovery of a number of underground obstructions, the schedule is back on track with the foundations and structure of the basement levels now finished.

Read More

August

With the rainy season having given way to the annual onslaught of typhoons, the construction team in Azabudai has to contend with its share of wet weather in addition to the soaring summer temperatures.

Read More

June

In his first visit to the Azabudai site since the groundbreaking ceremony last September, Club President Lance Lee spent one late May morning taking in the massive scope of changes that have unfolded since construction began in early 2008.

Read More

 

March

The project passed a key milestone in March with the placement of the first permanent steelwork on the site, which will eventually become the beams and columns around the Bowling Center and Childcare Center.

Read More

2008

October

The demolition of the old Club buildings at Azabudai continued through the summer. This was followed by the start of excavation as crews began to work their way down the basement levels at the back of the former facility.

Read More

September

With as many as 150 dump truck loads moving every day through the construction site at Azabudai, the excavation phase has been a high-traffic, extremely systematic affair.

Read More

July

Following presentations by Pelli Clarke Pelli this spring, the local consulting teams have been plugging away to finalize details of the new Club in Azabudai and obtain government approval for the permits needed to begin construction.

Read More

May

Renowned architect Cesar Pelli of Pelli Clarke Pelli, the firm behind the design of the new Azabudai Club, presented the design to the Membership on April 15.

Read More

January

Welcome to Takanawa! The Club is now settling into the temporary facility and we hope that everyone is again making use of their old favorites...

Read More

2007

November

It’s full steam ahead for the Club’s move to Takanawa, with everything on schedule and progressing according to plan...

Read More

October

The move to the temporary Club at Takanawa is quickly approaching and the project is progressing rapidly indeed, with construction on schedule...

Read More

September

There was no summer lull for the Redevelopment Project, with construction at Takanawa keeping to its tight deadlines and design development...

Read More

August

Only in Japan! The new facility at Takanawa is taking shape with amazing speed...

Read More

July

The foundations are complete, the concrete for the ground floor has been poured and the steel columns are starting to go up for our facility at Takanawa...

Read More

June

Takanawa construction is progressing full steam. The foundations are being dug and the concrete pouring will start during the first week of June...

Read More

May

The floor plans and exterior for the Club at Takanawa have been finalized and approved by the LRPC and Board of Governors...

Read More

May 9: Special Update

The Club took the next step in its continuing evolution on May 9 when Masato Taki from Takanawa Shrine led a groundbreaking ceremony...

Read More

April

The Takanawa floor plans and exterior designs have been completed and approved by the LRPC and Board of Govenors...

Read More

2006

December

By the end of the year the project will be well positioned to move into the detailed design and planning stages through 2007...

Read More

November

PCPA met with, among others, the LRPC and management in the middle of November, and have now agreed all of the locations of the Member facilities within the Club...

Read More

October

The survey results of the Membership survey have been published, which underlines the trend toward the Club providing more informal dining facilities and recreation and sports facilities...

Read More

September

A kickoff meeting has been held with PCPA and provisional dates have been agreed for workshops to be held in Tokyo...

Read More

August

The Membership survey was mailed to all Members at the end of July and all responses sent to the McMahon Group for analysis at the beginning of September...

Read More

July

Following the successful completion of the pre-project stage, Pelli Clarke Pelli Architects (PCPA) was confirmed as the master design architect...

Read More

June

The master agreement between the Club and MEC was signed on June 30 and signals the beginning of the main project stage...

Read More

May

In the Special General Meeting held on May 23, the Membership gave a 93% approval for the Redevelopment Project to proceed... 

Read More